20April2024

header-actual2

 
School Construction
School Construction

School Construction

Until the start of our school project in early 2011, the village of Mushapo did not have their own school. To spare the children their daily long walk to neighboring villages and in order that more children can get a good education, ADH made the realization of a school project in Mushapo its goal. The school project is meant to last: Several school buildings with bright spacious classrooms of solid, durable materials should guarantee a permanent school operation no matter what the weather conditions. In addition, important new jobs will be created in the rural area by building schools and the operation thereof.

Dec 2013

Our end-of-the-year interim conclusion

In 2013, we started both south and north of Mushapo with the construction of school buildings. The first 20 x 4 meters large brick building in the north has been completed and is being used for school operations for two classes. The second 20 x 6 meters large building south of Mushapo is almost finished, but the completion is somewhat delayed. This building has two large classrooms for teaching, plus a staff room and a room for the headmaster. Beginning next year we will finish this brick building.  
Our end-of-the-year interim conclusion
Dec 2013

New approach needed for the development of a temporary building

For the conversion of a temporary building into a permanent one - a sturdy building with brick walls - we re-calculate to save materials and so minimize the costs. It is mainly due to the high transportation costs of materials, such as cement and iron, that they are here in the interior so much more expensive than, for example, in the capital. We get advice from the Denys team in Tshikapa and from Robert in Mushapo, who is very familiar with the construction of houses under the local conditions. We consider whether we actually should make this conversion.  
New approach needed for the development of a temporary building
Nov 2013

The growing number of students who need accommodation

To provide the unexpected increase in the number of pupils with a proper education and be placed in classrooms, we divide our temporary school buildings each in 3 classrooms (previously 2 rooms each). The buildings are large enough. In addition, we will repair another old farm house and change it provisionally into our fourth school building. In total there are now 10 classrooms for daily classes. However, this is only a temporary solution, because the simple buildings made of wood and clay must constantly be repaired.  
The growing number of students who need accommodation
Oct 2013

How do we respond to the continuing rise in student numbers?

Demand for classes at our school grew rapidly and we needed to respond to the ever-growing number of students and thus increasing class sizes. We had actually planned for fewer students, but also do not want to deny children from neighboring villages education at our school. Because the goal is a proper education, we should reduce the class sizes. For this we need to hire more teachers. Besides these unexpected extra costs there is also the space problem that we have to solve as soon as possible.
How do we respond to the continuing rise in student numbers?
Sep 2013

Construction work is progressing well

We visit the site of our second brick building. The construction of this building has seen great progress in recent months. The building is expected to be finished in a few months including the inside. Congratulations Jean, Robert and Laurent, representatives of the entire construction team for the so far well-done work.  
Construction work is progressing well
Jul 2013

The walls of the second building are raised

Concrete columns are now placed on the 20 x 6 meters large foundation and the walls are raised. For this we use the rest of the bricks that are left over from the last time we made them in April. However, these are not enough and to complete the masonry we need to make and burn new bricks again.  
The walls of the second building are raised
Jun 2013

Construction on the second building continues

Now that the first building is completed, we will continue with the building that we started last year on our property south of Mushapo. The foundations and the foundation walls are already in place. The surplus materials from the first building we have brought to the current site. First timber supports are installed on which the roof structure is placed. On this framework, the corrugated metal sheets are placed, which are fastened with nails to make the roof rain proof. This approach is primarily for the purpose that materials can be stored in a dry place and the workers can work under dry conditions.  
Construction on the second building continues
May 2013

First brick building is finished

The construction work is finished. The first school building made with bricks north of Mushapo on the old farm area, is ready. The school building has two large bright classroom. The building has many windows and the interior is painted white. The classrooms are equipped with benches, a teacher's desk and a blackboard.  
First brick building is finished

Page 6 of 9

 We'd like to be a positive example to other agencies and to encourage them to also engage in the interior.

Our objective – to counter urbanization

Newsletter

If you want to subscribe to our newsletter, please send us a message.

Subscribe

Contact us

Do you have any questions or comments for us? Contact us directly! We appreciate your message and will try to answer you as soon as possible.

Contact us

I want to help

You want to know how you can help us to help in Congo? Get to know more about how you can support us.

Help ADH